Equipment Validation

Objective

At the end of this session, student will be able to

       Discuss the principles of qualification of equipment, with specific focus on:

       The different stages of qualification

       Requalification and

       Qualification of “in use” equipment

       Discuss  the requirements for equipment

       Selection

       Design

       Use

       Maintenance

Equipment

Principle  

       Equipment must be

       Located

       Designed

       Constructed

       Adapted

       Maintained

       To suit the operations to be carried out

       Equipment layout and design must aim:

       to minimize risks of error

       to permit effective cleaning and maintenance

       To avoid

       cross-contamination, dust and dirt build-up

       any adverse effect on the quality of products

       Equipment must be installed to:

       minimize risks of error                  

       minimize risks of contamination

Balances and Measuring Equipment

       Appropriate range and precision available

       In production and quality control

         Calibrated

       Scheduled basis

       Checks

       Records maintained

Production equipment

       Appropriate design

       Easily and thoroughly cleaned on a scheduled basis

       procedures and records

       No hazard to the products

       Contact parts of suitable non-reactive materials

       Non additive and not absorptive

       Defective equipment

       Removed, or labelled to prevent use

       Closed equipment used when possible

       Open equipment, or when equipment opened, precautions taken to prevent contamination

       Non-dedicated equipment cleaned according to validated cleaning procedures between different products

       Current drawings of critical equipment and support systems maintained

Control laboratory equipment

       Equipment and instruments suitable for the tests to be performed

       Defective equipment

       Removed

       Labelled

Washing, cleaning and drying

       Equipment used for washing and drying – not the source of contamination

       Equipment design should promote easy cleaning

       Cleaning on scheduled basis, procedures and records

       Washing and cleaning

       Manual

       Automated (Clean in place (CIP), Steam in place (SIP))

Basic Principles of GMP

Possible Issues

       Poor design

       Lack of safety

       Poor quality finishes

       Lack of cleaning

       Lack of maintenance

       No usage log or record

       Use of inappropriate weighing equipment

       Open-plan location of compressing machines                                                                                   

Basic Principles of GMP

       Remember to look at punches and dies

       Are there specifications for these?

       How are they cleaned, stored, issued for use and returned to storage?

       Are they in a good condition and checked at regular intervals?

Validation

General

       Qualification policy for systems and equipment

       To include instruments used in production and quality control

       New systems and equipment: All stages of qualification applicable (DQ, IQ, OQ and PQ)

       In some cases: Not all stages of qualification may be required

e.g. electrical supply systems

       Qualification should be done in accordance with predetermined and approved qualification protocols

       The results of the qualification should be recorded and reflected in qualification reports

       The extent of the qualification should be based on the criticality of a system or equipment, e.g.

Blenders, autoclaves or computerized systems

       Qualification should be done in accordance with predetermined and approved qualification protocols

       The results of the qualification should be recorded and reflected in qualification reports

       The extent of the qualification should be based on the criticality of a system or equipment, e.g.

       Blenders, autoclaves or computerized systems

Qualification and Validation

Definitions

       Validation

       Action of proving, in accordance with the principles of GMP, that any procedure, process, equipment, material, activity or system actually leads to the expected results

        It is a process using documented evidence that provides a high degree of assurance that a specific process will consistently produce the predetermined outcome.

       Qualification

       Action of proving that any premises, systems and items of equipment work correctly and actually lead to the expected results

(Validation usually incorporates the concept of qualification)

       A process of establishing confidence that the equipment is capable of consistently operating within established limits and tolerances.  Studies therefore done prior to use

       Qualification

     - confirm compliance with specified requirements or criteria (Do you have the right tool for the job?)

-          Performed on one element or component of the process to be validated

-          Conduct tests to establish if the component of a process has the attributes to produce a specified outcome.

       Validation

    - Proof. Document that the process will consistently produce a predetermined outcome.

Validation

Stages of qualification

Design qualification

Installation qualification

Operational qualification

Performance qualification

General

Systems: Qualified before equipment

       Equipment: Qualified before routine use

       Systems and equipment: Periodic requalification, as well as requalification after change

       Certain stages done by the supplier or a third party

       Maintain the relevant documentation, e.g. standard operating procedures (SOPs), specifications and acceptance criteria, certificates and manuals

Design qualification

       User requirements should be considered when deciding on the specific design of a system or equipment

       A suitable supplier should be selected for the appropriate system or equipment (approved vendor)

Installation qualification

       Verifies that the correct equipment has been received and installed as per plan and protocol. Also that it is complete and undamaged (parts, services, controls, gauges and other components)

         Normally advised to prepare requirements for calibration, maintenance and cleaning at this stage

       Verifies that equipment has been properly installed and calibrated including connections to utilities.

       Calibrate the measuring, control and indicating devices against appropriate, traceable national or international standards

       Documented records for the installatio

       Installation qualification report

       Indicate satisfactory installation

       Include details, e.g.

       The supplier and manufacturer

       System or equipment name, model and serial number

       Date of installation

       Spare parts, relevant procedures and certificates

Operational qualification

       Systems and equipment should operate correctly – operation verified as in the qualification protocol

       Verifies that the equipment operates consistently within established limits and tolerances over the defined operating ranges.

       Studies on critical variable to include conditions encompassing upper and lower operating limits and circumstances (i.e.     “worst case conditions”)

       Challenges equipment functionally to verify compliance with manufacturer’s specifications and end – user defined requirements. To include verification of operation of all system elements, parts, services, controls, gauges and other components

       Documented records (Operational qualification report)

       Finalize and approve SOP (operation)

       Training of operators provided – training records

       Systems and equipment released for routine use after completion of operational qualification, provided that:

       All calibration, cleaning, maintenance, training and related tests and results were found to be acceptable

How many runs are to be performed during Operational Qualification (OQ) testing?

       Guidelines stress the importance of equipment qualification simulating actual production conditions, including 'worst case' situations and that "tests and challenges should be repeated a sufficient number of times to assure reliable and meaningful results."

       "three consecutive batches"  is recommended for process validation rather than for equipment qualification.  No specific number of "runs" for equipment qualification, but multiple tests to simulate actual operating ranges and to establish consistency are expected

Qualification of Equipment

If one type and model of equipment is qualified, can it be used in a different process without additional qualification?

       For IQ document whether each equipment is installed correctly and operates consistently according to established limits and tolerances. OQ should also be performed for each different use of the equipment or system to document the suitability for that use

       Not be required for additional pieces of the same type/model of equipment when used in the same process or  for each piece of the same type/model of equipment used in the same process, provided installation qualification has been performed

Performance qualification

       Verifies that the equipment performs according to design specifications and user defined requirements in a reliable and reproducible manner under normal production conditions

       Verified in accordance with a performance qualification protocol

       Documented records  – performance qualification report

       Show satisfactory performance over a period of time i,e. carried out long enough to prove that the equipment is under control and turns out product of specified quality consistently.

       Manufacturers to justify the selected period

Qualification Plan

       To ensure that requirements are met and confirm by examination and collection of objective evidence

        Challenges to equipment to be designed

        Re-create intended use

        Test, Test, Test

  1. Purpose
  2. Scope
  3. Equipment Description
  4. Operational Specifications
  5. Acceptance Criteria
  6. Testing Results
  7. Discrepancies/Corrective Actions
  8. Conclusions/Final Report

"A qualification protocol / report"

       It reflects the minimum information that should be included

       This is an example – and should be used as such

       Specific formats need to be designed for a specific system or piece of equipment

Worst Case Scenarios

       Conditions that include upper and lower processing limits

       Circumstances that present the highest chance of process or product failure relative to ideal situations

       Identify those conditions that are likely to be experienced during routine manufacture/process

More Examples

The following case illustrates the importance of performing adequate equipment qualification on each piece of processing equipment

       A pharmaceutical firm used two blenders to produce a tablet. Both blenders from  same equipment manufacturer, same model number and same design. Supplier told the drug manufacturer that the units were "identical."  though one was older. Manufacturer did not include the older blender as part of its process validation.

More Examples

       Company marketed about 100 batches of tablets using the old blender. Retention samples showed some  batches failed content uniformity

       investigation showed out of specification  batches  were from one of the two "identical" blenders – the  old one. The older blender had a slightly smaller capacity and different operational characteristics (RPMs) when run at the same settings as the newer blender.

       Subsequently, the firm recalled its total production of the product it made using the older blender. The firm decided to qualify the old blender using production size lots.

Qualification of “Old” Equipment

       What about "old manufacturers" who have not performed DQ, or IQ for existing, in-use systems and/or equipment?

       It is not always possible to have all details for IQ  or OQ for established equipment. The manufacturer should however have data that verifies the operating parameters and limits for the critical variables of the equipment. In addition, calibration, cleaning, preventative maintenance, operating procedures and operator training procedures for the use of the equipment should be documented and used as SOPs  ……. PIC/S

Qualification of “in-use” systems and equipment

       Data to support and verify the suitable operation and performance of systems and equipment

       Should include operating parameters and limits for critical variables, calibration, maintenance and preventive maintenance, standard operating procedures (SOPs) and records

Risk assessment of operations or functions

Qualification flow Scheme
(extracted from CEFIC Guidance)

Example of Document Matrix

Requalification

       Required for:

       Significant change in batch size

       Change in operating parameters

       Component specifications have changed

       New accessories or components are added to previously qualified equipment

       Process changes that potentially impact product effectiveness or quality

Some Experiences

What if the results are not good?

       Study report destroyed and manufacturer pretends it never happened So what should be done?

       Document the study, but don’t approve it

       Identify and describe any corrective actions needed or any noteworthy observations or deviations

       Start another study using the findings and conclusions  from the failed study

More experiences – poor qualification reports

       Specifications not approved

       Failure to provide clear, complete instructions in the protocol

       Instrument calibration records or status not included

       Full range of intended operating parameters not challenged

       Inadequate sample sizes

       Atypical data points

       Unexplained deviations from protocol

       Inconsistencies between final report and data collection/recording forms

WHO References

       Good manufacturing practices (GMP):  guidelines on the validation of manufacturing processes

       Validation of analytical procedures used in the examination of pharmaceutical materials

Summary

       Stages of qualification  are  design qualification, installation qualification , performance qualification etc

       Systems: Qualified before equipment

       Equipment: Qualified before routine use

       Systems and equipment: Periodic requalification, as well as requalification after change

       Certain stages done by the supplier or a third party

       Maintain the relevant documentation

        PQ verifies that the equipment performs according to design specifications and user defined requirements in a reliable and reproducible manner under normal production conditions

 

                                               

 